We are dedicated to the upkeep and improvement of CNC. We take pride in managing the operation and maintenance of the campus infrastructure, including building repairs, building automation systems, renovations and construction, landscaping, and capital projects.
Campus Access & Updates
Stay informed. Bookmark this page to get the latest updates on construction activity, access changes, and project timelines across campus. This page is updated regularly to help you plan ahead.
Need help navigating campus? View all accessible doors throughout the Main Building.
Building Envelope Project
Building envelope work continues across the Prince George Campus through November.
Current work includes exterior finishing in the 200, 300 and 500 Blocks, soffit framing and perimeter lighting preparation in the 400 Block, and landscaping around the main courtyard.
Scaffolding and skylight replacement work are underway at the 700 Block, including the Main Entrance atrium. Work after 4:00pm may cause construction noise and temporary disruptions to nearby services.
Upcoming activities include sidewalk replacement near the 500 Block entrance, stair finishing in the 300 Block, and continued skylight replacement through November.
The Main Entrance and second-floor Learning Commons remain open during construction. Temporary route changes may be needed near active work areas.
100 Block Washroom Renovations
Renovations to the two washrooms on the 3rd floor of the 100 Block began Thursday, October 8. Both washrooms are closed during construction, with work expected to continue until mid-December.
Please use alternate washrooms while work is underway.
700 Block Exterior Lighting Update
The new exterior lights around the 700 Block have been installed but are not yet fully functioning. The lighting control system is awaiting final programming.
In the meantime, the lights will remain on to help maintain exterior lighting and support campus security.
Thank you for your patience while this work is completed.
Accessibility & Detours
Accessible parking at the South Main Entrance is temporarily relocated near the crosswalk ramp.
The following entrances and exits remain closed:
East Entrance
Two 1st-floor exits in the 300 Block
Back entrance of the Health and Wellness Centre (closed except for emergencies)
Temporary route changes may be needed near active scaffolding work, including the corridor outside the Learning Commons.
Please follow posted signage and allow extra time when travelling through campus.
For detailed updates on each project, click on Current Updates below.
Edited: October 28, 2026
Current Projects
Building Envelope Project
The Building Envelope Project at CNC’s Prince George campus, funded by the Ministry of Infrastructure, enhances campus sustainability and energy efficiency for a resilient, future-ready environment.
Wayfinding Project
The Wayfinding Project at the Prince George Campus improves campus navigation with clear, accessible signage while creating a more connected and welcoming environment for students, employees, and visitors.
100 Block Washroom Renovations
Renovations to the two washrooms on the 3rd floor of the 100 Block are tentatively scheduled to begin in early October and continue until mid-December 2026. Both washrooms will be closed during construction. Please use alternate washrooms during this time.
Completed Projects
Network Renewal
Network Renewal
Main Entrance Renewal
Main Entrance Renewal
500 Block Flooring
500 Block Flooring
Transit Shelter Upgrade
Transit Shelter Upgrade
Main Entrance Art Installation
Main Entrance Art InstallationFrequently Asked Questions
While building improvement projects bring many benefits, they also involve some short-term inconveniences. During construction projects, you may experience:
- Temporary re-routing to alternate entrances and exits,
- Closure of areas where construction is occurring,
- Increased noise levels, and
- Potential localized disruptions to utilities.
Efforts are made to minimize disruption. However, despite our best efforts, some construction-related inconveniences are unavoidable. We appreciate your understanding and cooperation as we work towards enhancing our facilities. Staying informed through our official updates will help you navigate any changes and ensure a smooth transition during this period.
Yes, alternate routes are typically provided to ensure safe access to campus buildings. Information on these routes will be posted around campus and online.
Accessibility is a priority. Alternative accessible routes and temporary facilities will be provided to accommodate all students, staff, and visitors.
For questions or concerns, contact the campus facilities department.