Building Envelope Project Update: East and South Sides of 700 Block Work Continues

    • Prince George
  • June 16, 2025
062025 700 Block (6)

Current Updates 

Stay informed with regular updates as construction progresses. We’ll keep you posted on project milestones, potential disruptions, and other important details.

Demolition and installation of the new building envelope continue along the east and south walls of the 700 Block, affecting the ARC, International Education, Office of the Registrar, Student Services, and the Learning Commons.

Upcoming Activities

Week of June 29 - July 12

Location: 700 Block, Main Campus Building

Scope of Work: Ongoing demolition and installation of the first components of the new building envelope along the east and south exterior walls. Work is currently affecting areas near the ARC, International Education, Office of the Registrar, Student Services, and the Learning Commons.

 Expected Impacts:

🔊 Noise: Elevated noise levels throughout the week.

🚧 Access: Temporary alternate routes will be in place.

👷 Visual disruptions in the work zones.

Safety Reminder

  • Please follow all posted signage and detour instructions.
  • For your safety, do not enter active construction zones.

About the Project 

The Building Envelope Project is designed to enhance the exterior of the Prince George campus with energy-efficient upgrades, a modernized aesthetic, and a focus on long-term sustainability. These improvements will provide a more comfortable, energy-efficient space for everyone at CNC while ensuring that our facilities remain resilient for generations to come.  

This project is made possible with restricted capital funding by the Ministry of Infrastructure. 

The Building Envelope Project aligns with CNC’s Strategic Plan (lhulh whuts’odutel’eh – Learning Together) under Priority 3.5: Rejuvenate College Infrastructure. Specifically, it supports objectives 3.5.1 through 3.5.4 by upgrading campus infrastructure, revitalizing learning spaces, improving sustainability, and helping reduce the college’s overall carbon footprint.

Key Highlights of the Project: 

  • Energy-efficient upgrades for better sustainability.
  • A modernized campus exterior to reflect our commitment to innovation.
  • Long-term durability to ensure the campus remains functional and eco-friendly for years to come.  

Project Timeline

  • March 2025: Pre-construction preparations and site setup begin.
  • April 11:Pre-construction phase
  • April 25:Transition to Demolition Stage
  • May 2025: Official construction begins.
  • May 9, 2025: Demolition work on the 100 Block started
  • June 8, 2025: 100 Block work largely complete. Demolition work on the 700 Block started.
  • June 15, 2025: Demolition work on the east and south side of the 700 Block continues.
  • July 2, 2025: Installation of initial building envelope components at the east and south side of the 700 Block started.
  • Duration: Approximately 2 years 
  • Completion Date: May 2027 (estimated) 

Impact on Campus

We are committed to minimizing disruptions during construction. While work is taking place, we will keep staff, students and visitors informed about: 

  • Campus accessibility 
  • Potential disruptions 
  • Changes to parking and entrances 

Our team is focused on ensuring that the impact on your daily experience is as minimal as possible. 