Current Updates
Stay informed with regular updates as construction progresses. We’ll keep you posted on project milestones, potential disruptions, and other important details.
Construction continues across the Prince George Campus with work in the 100, 500, and 700 Blocks. The Weight Room and 500 Block 2nd floor are now open. West entrance detour has been lifted.
Accessible parking near the Main Entrance has been relocated to the crosswalk ramp, and a detour is in place for those walking from the east side.
Check the full map to see how campus blocks are connected and where work is taking place.
Upcoming Activities
Week of December 8 - 14
100 Block:
- Continuing install of moisture barrier shield, exterior insulation, and metal framing
- Painting of interior window trim. North and south side areas remain restricted.
- Installation of exterior window flashings
300 Block:
- Continue installing foundations and patching concrete
700 Block:
- Additional framing for lighting
- Roof installation
- 1st floor window replacement work is underway, spanning from the south side of the Main Entrance to the East Entrance until Dec 19th
- Installation of exterior insulation, exterior window flashings, and metal framing
Week of December 15 - 21
700 Block:
- Additional framing for lighting
- 1st floor window replacement work is underway, spanning from the south side of the Main Entrance to the East Entrance until Dec 19th
Expected Impacts:
🔊 Noise: Elevated noise levels.
🚧 Access: Temporary alternate routes and partial entrance closures. Small detour at the west entrance during stair replacement.
🚫 Closures: Weight Room and second level of 500 Block closed until further notice. Bike rack at west entrance closed until end of October.
👷 Visibility: Ongoing construction activity and visual disruptions in affected areas.
Safety Reminder
- Please follow all posted signage and detour instructions.
- For your safety, do not enter active construction zones.
About the Project
The Building Envelope Project is designed to enhance the exterior of the Prince George campus with energy-efficient upgrades, a modernized aesthetic, and a focus on long-term sustainability. These improvements will provide a more comfortable, energy-efficient space for everyone at CNC while maintaining our facilities’ resilience well into the future.
This project is made possible with restricted capital funding by the Ministry of Infrastructure.
The Building Envelope Project aligns with CNC’s Strategic Plan (lhulh whuts’odutel’eh – Learning Together) under Priority 3.5: Rejuvenate College Infrastructure. Specifically, it supports objectives 3.5.1 through 3.5.4 by upgrading campus infrastructure, revitalizing learning spaces, improving sustainability, and helping reduce the college’s overall carbon footprint.
Key Highlights of the Project:
- Energy-efficient upgrades for better sustainability.
- A modernized campus exterior to reflect our commitment to innovation.
- Long-term durability to ensure the campus remains functional and eco-friendly for years to come.
Project Timeline
- March 2025: Pre-construction preparations and site setup begin.
- April 11:Pre-construction phase
- April 25:Transition to demolition stage.
- May 2025: Official construction begins.
- May 9, 2025: Demolition work on the 100 Block started
- June 8, 2025: 100 Block demolition work largely complete. Demolition work on the 700 Block started.
- June 15, 2025: Demolition work on the east and south side of the 700 Block continues.
- July 2, 2025: Installation of initial building envelope components at the east and south side of the 700 Block started.
- August 11, 2025: Roof work, brick façade and wall stucco removal on the 700 Block started
- August 18, 2025: Penthouse demolition and landscaping work on the 700 Block started
- September 4, 2025: Elevated walkway work on the 300 Block started
- September 8, 2025: Window replacement work on the 100 Block started. Moisture shield barrier installation on 100 Block started.
- October 14, 2025: Sidewalk and foundation removal at the west entrance of the 500 Block for stair replacement started.
- October 20, 2025: 100 Block interior window trims work start. 700 Block brick façade almost done.
- November 25, 2025: 500 block stairs installed. Weight room and 2nd floor open. Slight detour in West Entrance lifted
- November 26 , 2025: 700 block, 1st floor window replacement
- Duration: Approximately 2 years
- Completion Date: May 2027 (estimated)
Impact on Campus
We are committed to minimizing disruptions during construction. While work is taking place, we will keep staff, students and visitors informed about:
- Campus accessibility
- Potential disruptions
- Changes to parking and entrances
Our team is focused on ensuring that the impact on your daily experience is as minimal as possible.