Get ready for a fresh look at the main entrance at our Prince George Campus. We're thrilled to announce an upcoming renovation project that's all about enhancing accessibility, safety, and aesthetics.
Why the Change?
We're addressing some maintenance concerns with the current brick and concrete setup at the entrance. Over time, nature's elements have played a part in water and ice accumulation—creating a slip hazard. Safety first, always!
What's in Store
- Fresh concrete for a dry and safe entry experience.
- Goodbye to the grand concrete arches outside the entrance, and hello to improved visibility and sight lines.
- New green spaces and flower beds, adding charm between the entrance and the amphitheater.
- A wider sidewalk along those short-term parking spots.
Alternate Routes
While the magic happens, the main campus entrance will temporarily shift to the west side (between the dental and daycare building and the gym). It's a breeze to access, and we've got accessibility in mind with a handy door actuator. Bonus: it's conveniently close to our campus transit shelters.
Smoking Area Update
The smoking area has been relocated to the benches outside of the East Entrance – watch for signs pointing to the way.
Project Timeline
- August 10: Construction fencing goes up.
- August 14: Demolition begins.
- August 28: Main entrance temporarily closed.
- September 18:
- Concrete arches, slabs, and sidewalk have been removed.
- Rough site grading is underway.
- Drainage catch basin installation has started.
- November 30: planned project completion, with landscaping taking place in the spring of 2024.
Stay tuned for more updates, and thanks for your patience as we improve our campus.