Current Updates
Stay informed with regular updates as construction progresses. We’ll keep you posted on project milestones, potential disruptions, and other important details.
Construction continues across the 100, 300, 500, and 700 Blocks through September. Expect elevated noise, temporary exit closures, and some pedestrian detours while crews work on roofs, exterior walls, moisture barriers, stair removal, and elevated walkways. The 700 Block main entrance is partially closed until further notice and select exits in the 100 Block will be closed for safety.
Accessible parking near the Main Entrance has been relocated to the crosswalk ramp, and a detour is in place for those walking from the east side.
Check the full map to see how campus blocks are connected and where work is taking place.
Upcoming Activities
Week of September 8 – 14
700 Block
Roof: Continue demolition and installation work
West Side:
- Removal of brick façade
- Penthouse demolition of existing stucco (stairs and common areas above IT Helpdesk)
- Landscaping
100 Block:
- Moisture shield installation. Exits on the 1st floor east entrance and the 2nd floor leading to the Facilities will be closed.
- Windows removal and demolition on classroom 2-122. Noise may impact surrounding classrooms on all 3 floors
300 Block: Elevated walkway layout coring and cutting, landscaping
Week of September 15 – 21
700 Block
Roof: Continue demolition and installation work
West Side:
- Removal of brick façade
- Penthouse demolition of existing stucco (stairs and common areas above IT Helpdesk)
- Landscaping
100 Block:
- Moisture shield installation. Exits on the 1st floor east entrance and the 2nd floor leading to the Facilities will be closed.
- Windows removal and demolition
300 Block:
- Elevated walkway demo, layout coring and cutting
- Landscaping
Week of September 22 – 28
700 Block
Roof: Continue demolition and installation work
West Side:
- Removal of brick façade
- Penthouse demolition of existing stucco (stairs and common areas above IT Helpdesk)
- Windows removal and demolition
100 Block:
- Moisture shield installation. Exits on the 1st floor east entrance and the 2nd floor leading to the Facilities will be closed.
- Windows removal and demolition
300 Block:
- Elevated walkway demo, layout coring and cutting
500 Block: Stair removal
Expected Impacts:
🔊 Noise: Elevated noise levels.
🚧 Access: Temporary alternate routes will be in place.
👷 Visual disruptions in the work zones.
Safety Reminder
- Please follow all posted signage and detour instructions.
- For your safety, do not enter active construction zones.
About the Project
The Building Envelope Project is designed to enhance the exterior of the Prince George campus with energy-efficient upgrades, a modernized aesthetic, and a focus on long-term sustainability. These improvements will provide a more comfortable, energy-efficient space for everyone at CNC while maintaining our facilities’ resilience well into the future.
This project is made possible with restricted capital funding by the Ministry of Infrastructure.
The Building Envelope Project aligns with CNC’s Strategic Plan (lhulh whuts’odutel’eh – Learning Together) under Priority 3.5: Rejuvenate College Infrastructure. Specifically, it supports objectives 3.5.1 through 3.5.4 by upgrading campus infrastructure, revitalizing learning spaces, improving sustainability, and helping reduce the college’s overall carbon footprint.
Key Highlights of the Project:
- Energy-efficient upgrades for better sustainability.
- A modernized campus exterior to reflect our commitment to innovation.
- Long-term durability to ensure the campus remains functional and eco-friendly for years to come.
Project Timeline
- March 2025: Pre-construction preparations and site setup begin.
- April 11:Pre-construction phase
- April 25:Transition to demolition stage.
- May 2025: Official construction begins.
- May 9, 2025: Demolition work on the 100 Block started
- June 8, 2025: 100 Block demolition work largely complete. Demolition work on the 700 Block started.
- June 15, 2025: Demolition work on the east and south side of the 700 Block continues.
- July 2, 2025: Installation of initial building envelope components at the east and south side of the 700 Block started.
- Duration: Approximately 2 years
- Completion Date: May 2027 (estimated)
Impact on Campus
We are committed to minimizing disruptions during construction. While work is taking place, we will keep staff, students and visitors informed about:
- Campus accessibility
- Potential disruptions
- Changes to parking and entrances
Our team is focused on ensuring that the impact on your daily experience is as minimal as possible.