Building Envelope Project Update: August 2025 Updates

    • Prince George
  • July 7, 2025
081025 Construction

Current Updates 

Stay informed with regular updates as construction progresses. We’ll keep you posted on project milestones, potential disruptions, and other important details.

Throughout August, crews will finalize demolition cleanup in the 100 Block, remove fins at the 200 Block (closing the cafeteria’s back exit and path), and continue work on the 700 Block with entrance closures, exterior lighting demolition, brick façade removal, panel installation, and roof upgrades. Accessible parking near the Main Entrance has been relocated to the crosswalk ramp, and a detour is in place for those walking from the east side.

Check the full map to see how campus blocks are connected and where work is taking place.

Upcoming Activities

Week of August 11 - 17

100 Block
• Finalization of demolition clean-up – remaining stucco debris removal

200 Block
• Removal of fins at the back entrance of the cafeteria – exit and concrete path closed

700 Block
• Installation of initial building envelope components
Roof: Continue demolition and installation work
Main Entrance:
• Fully closed August 11–14; reopens August 18
• Exterior lighting demolition

Week of August 18 - 24

700 Block

Roof: Continue demolition and installation work
West Side:
• Removal of brick façade
• Penthouse demolition of existing stucco
• Installation of paneling and initial building envelope components
• Start electrical installation for new exterior lights

Week of August 25 - 31

700 Block

Roof: Continue demolition and installation work
West Side:
• Removal of brick façade
• Penthouse demolition of existing stucco
• Installation of paneling and initial building envelope components
• Continue electrical installation for new exterior lights

Accessibility & Detours:

Please use posted detour routes and alternate entrances during closures. The 700 Block main entrance will be closed August 11–14, with access available again starting Monday, August 18. Back entrance to the cafeteria (200 Block) will be closed during fin removal.

Expect noise, dust, and temporary pedestrian rerouting in affected areas.

Expected Impacts:

🔊 Noise: Elevated noise levels.

🚧 Access: Temporary alternate routes will be in place.

👷 Visual disruptions in the work zones.

Safety Reminder

  • Please follow all posted signage and detour instructions.
  • For your safety, do not enter active construction zones.

About the Project 

The Building Envelope Project is designed to enhance the exterior of the Prince George campus with energy-efficient upgrades, a modernized aesthetic, and a focus on long-term sustainability. These improvements will provide a more comfortable, energy-efficient space for everyone at CNC while maintaining our facilities’ resilience well into the future.

This project is made possible with restricted capital funding by the Ministry of Infrastructure. 

The Building Envelope Project aligns with CNC’s Strategic Plan (lhulh whuts’odutel’eh – Learning Together) under Priority 3.5: Rejuvenate College Infrastructure. Specifically, it supports objectives 3.5.1 through 3.5.4 by upgrading campus infrastructure, revitalizing learning spaces, improving sustainability, and helping reduce the college’s overall carbon footprint.

Key Highlights of the Project: 

  • Energy-efficient upgrades for better sustainability.
  • A modernized campus exterior to reflect our commitment to innovation.
  • Long-term durability to ensure the campus remains functional and eco-friendly for years to come.  

Project Timeline

  • March 2025: Pre-construction preparations and site setup begin.
  • April 11:Pre-construction phase
  • April 25:Transition to demolition stage.
  • May 2025: Official construction begins.
  • May 9, 2025: Demolition work on the 100 Block started
  • June 8, 2025: 100 Block demolition work largely complete. Demolition work on the 700 Block started.
  • June 15, 2025: Demolition work on the east and south side of the 700 Block continues.
  • July 2, 2025: Installation of initial building envelope components at the east and south side of the 700 Block started.
  • Duration: Approximately 2 years 
  • Completion Date: May 2027 (estimated) 

Impact on Campus

We are committed to minimizing disruptions during construction. While work is taking place, we will keep staff, students and visitors informed about: 

  • Campus accessibility 
  • Potential disruptions 
  • Changes to parking and entrances 

Our team is focused on ensuring that the impact on your daily experience is as minimal as possible. 

Your voice is important

Would you like for your story to be featured on the CNC site? Get in touch!
Share your story with us

Contact Media Relations media@cnc.bc.ca