Building Envelope Project Update

    • Prince George
  • October 1, 2026

Current Updates 

Stay informed with regular updates as construction progresses. We’ll keep you posted on project milestones, potential disruptions, and other important details.

Building envelope work continues across the Prince George Campus. Current activities include siding and trim installation, canopy and stair work, landscaping, soffit work, painting, and other exterior finishing.

Work is taking place in the 200, 300, 400, and 700 Blocks, as well as the main courtyard. Through October, crews will continue exterior finishing and landscaping, with skylight work planned at the 700 Block later in the month.

Accessible parking near the Main Entrance has been relocated until further notice to the crosswalk ramp, and a detour is in place for those walking from the east side.

Check the full map to see how campus blocks are connected and where work is taking place.

Expected Impacts

🔊 Noise: Construction noise is expected from siding, canopy, stair, soffit, and skylight work.

🚧 Access: Temporary barriers and localized detours may be in place near active work areas. Please follow posted signage and use alternate routes where required.

🌱 Landscaping: Landscaping continues in the main courtyard, including paving stone removal and landscaping work.

👷 Construction Activity: Siding, trim, painting, canopy work, soffit framing, landscaping, skylight work, and other finishing activities will continue across several areas of campus.

Please allow extra time when travelling through campus and use alternate routes where required.

Upcoming Activities

September 28–October 4

200 Block

  • Install trim and exterior siding

300 Block

  • Complete demolition of the garbage enclosure
  • Install stair treads

300 Block South

  • Install wood-look siding on the courtyard side
  • Install canopy framing near the gym

400 Block

  • Install spray foam insulation at exterior soffits during the weekend
  • Install soffit framing for perimeter lighting

700 Block

  • Paint exterior stair handrails 

Main Courtyard

  • Continue landscaping 🌱

October 5–11

200 Block

  • Continue trim and siding installation

300 Block South

  • Continue wood-look siding installation on the courtyard side

300 Block North

  • Install trim and exterior panels

400 Block

  • Continue soffit framing for perimeter lighting

700 Block

  • General exterior cleanup
  • Prepare grades for sod 🌱
  • Complete interior painting
  • Install red exterior panels
  • Continue mechanical penthouse siding

Main Courtyard

  • Continue landscaping 🌱

October 12–18

200 Block

  • Continue trim and siding installation

300 Block North

  • Continue trim and exterior panel installation

400 Block

  • Continue soffit framing for perimeter lighting

700 Block

  • Tentative scaffold installation for upcoming skylight work
  • Complete deficiency work
  • Continue mechanical penthouse siding

Main Courtyard

  • Continue landscaping 🌱

October 19–25

200 Block

  • Continue exterior finish panel installation

300 Block North

  • Continue trim and exterior panel installation

400 Block

  • Install perimeter lighting

700 Block

  • Skylight demolition and installation
  • Continue skylight scaffold work

Main Courtyard

  • Continue landscaping 🌱

    About the Project

    The Building Envelope Project is designed to enhance the exterior of the Prince George Campus through energy-efficient upgrades, improved sustainability, and long-term infrastructure renewal. These improvements will help create a more comfortable and resilient campus for students, employees, and visitors.

    This project is made possible with restricted capital funding by the Ministry of Infrastructure. 

    The Building Envelope Project supports CNC’s Strategic Plan (lhulh whuts’odutel’eh – Learning Together) under Priority 3.5: Rejuvenate College Infrastructure. Specifically, it supports objectives 3.5.1 through 3.5.4 by upgrading campus infrastructure, revitalizing learning spaces, improving sustainability, and helping reduce the college’s overall carbon footprint.

    Key Highlights of the Project: 

    • Energy-efficient building upgrades
    • Modernized campus exterior
    • Improved long-term durability and sustainability

    Project Timeline

    • March 2025: Project mobilization and site preparation
    • May 2025: Construction begins
    • Summer–Fall 2025: Demolition and exterior renewal work
    • Winter 2025–26: Interior and exterior finishing activities
    • Spring 2026: Major exterior upgrades continue across campus
    • Estimated Completion: May 2027

    Impact on Campus

    We are committed to minimizing disruptions during construction. Updates will be provided regarding:

    • Campus accessibility
    • Temporary disruptions and detours
    • Changes to parking, entrances, and pedestrian routes

    Our team is focused on ensuring that the impact on your daily experience is as minimal as possible. 

    Building Envelope Project FAQ

    Why does some of the new siding look wavy?

    Some members of the campus community may notice slight waviness or “ripples” in portions of the new metal siding. This effect, known as oil canning, is a common characteristic of flat metal siding and is widely recognized across the construction industry. 

    Oil canning is a visual effect only. It does not affect the strength, safety, durability, or weather protection of the building. The project team continues to monitor installation quality to ensure the work meets project requirements and industry standards. 

    The effect is often more noticeable in certain lighting and typically becomes less noticeable over time. 

    Read more about siding appearance

    Questions?

    construction@cnc.bc.ca

    Your voice is important

    Would you like for your story to be featured on the CNC site? Get in touch!
    Share your story with us

    Contact Media Relations media@cnc.bc.ca