Stay informed with regular updates as construction progresses. We’ll keep you posted on project milestones, potential disruptions, and other important details.
Building envelope work continues across the Prince George Campus. Current activities include window replacement, landscaping, insulation, siding and panel installation, exterior painting, perimeter lighting, canopy work, and other exterior finishing.
Work is taking place in the 100, 200, 300, 400, and 700 Blocks. Through September, crews will continue work on the 300 Block windows and canopy, exterior finishes in several areas, and landscaping preparation around campus.
Accessible parking near the Main Entrance has been relocated until further notice to the crosswalk ramp, and a detour is in place for those walking from the east side.
Check the full map to see how campus blocks are connected and where work is taking place.
Expected Impacts
🔊 Noise: Construction noise is expected from window replacement, exterior wall work, canopy installation, stair work, siding installation, and metal framing. Increased noise is expected in the 300 Block North later in September during installation of clips and metal framing.
🚧 Access: Temporary barriers and localized detours may be in place near active work areas. Please follow posted signage and use alternate routes where required.
🪟 Window Replacement: Window replacement continues in the 300 Block North. Work is scheduled in several first-, second-, and third-floor areas through mid-September.
👷 Construction Activity: Landscaping, insulation, siding, perimeter lighting, painting, canopy work, and exterior finishing will continue across several areas of campus.
Please follow posted signage and allow extra time when travelling through construction areas.
Upcoming Activities
September 7–13
100 Block
- Prepare grades for landscaping
200 Block
- Install insulation and trim
- Continue exterior siding and panel work
300 Block South
- Prepare for the new courtyard canopy near the gym
300 Block
- Window replacement continues
- Paint stucco wall near the bridge
- Paint the loading dock area
300 Block North
- Repair air barrier
- Install insulation
400 Block
- Install spray foam insulation in soffits during the weekend
- Frame soffits for perimeter lighting
700 Block
- Complete perimeter lighting installation
- Prepare grades for landscaping
- Continue deficiency work
- Install red exterior panels
- Continue mechanical penthouse siding
September 14–20
100 Block
- Continue preparation for landscaping
200 Block
- Continue exterior panel installation
300 Block South
- Continue preparation for the new canopy
300 Block
- Demolish the existing garbage enclosure near the loading dock
300 Block North
- Continue insulation installation
400 Block
- Install spray foam insulation in soffits during the weekend
- Continue framing soffits for perimeter lighting
700 Block
- Prepare grades for landscaping
- Continue installation of red exterior panels
- Continue mechanical penthouse siding
September 21–27
200 Block
- Continue exterior panel installation
300 Block South
- Install main-floor siding and panels
- Install new canopy
300 Block
300 Block North
- Install clips and metal framing 🔊
- Install trim and siding
400 Block
- Continue framing soffits for perimeter lighting
700 Block
- Clean up materials and crates
Main Entrance
- Tentative scaffold installation for skylight work
September 28–October 4
300 Block South
- Continue main-floor siding and panel installation
300 Block
- Continue stair tread installation
300 Block North
- Continue trim and siding installation
Main Entrance
- Tentative skylight scaffold installation
About the Project
The Building Envelope Project is designed to enhance the exterior of the Prince George Campus through energy-efficient upgrades, improved sustainability, and long-term infrastructure renewal. These improvements will help create a more comfortable and resilient campus for students, employees, and visitors.
This project is made possible with restricted capital funding by the Ministry of Infrastructure.
The Building Envelope Project supports CNC’s Strategic Plan (lhulh whuts’odutel’eh – Learning Together) under Priority 3.5: Rejuvenate College Infrastructure. Specifically, it supports objectives 3.5.1 through 3.5.4 by upgrading campus infrastructure, revitalizing learning spaces, improving sustainability, and helping reduce the college’s overall carbon footprint.
Key Highlights of the Project:
- Energy-efficient building upgrades
- Modernized campus exterior
- Improved long-term durability and sustainability
Project Timeline
- March 2025: Project mobilization and site preparation
- May 2025: Construction begins
- Summer–Fall 2025: Demolition and exterior renewal work
- Winter 2025–26: Interior and exterior finishing activities
- Spring 2026: Major exterior upgrades continue across campus
- Estimated Completion: May 2027
Impact on Campus
We are committed to minimizing disruptions during construction. Updates will be provided regarding:
- Campus accessibility
- Temporary disruptions and detours
- Changes to parking, entrances, and pedestrian routes
Our team is focused on ensuring that the impact on your daily experience is as minimal as possible.
Building Envelope Project FAQ
Why does some of the new siding look wavy?
Some members of the campus community may notice slight waviness or “ripples” in portions of the new metal siding. This effect, known as oil canning, is a common characteristic of flat metal siding and is widely recognized across the construction industry.
Oil canning is a visual effect only. It does not affect the strength, safety, durability, or weather protection of the building. The project team continues to monitor installation quality to ensure the work meets project requirements and industry standards.
The effect is often more noticeable in certain lighting and typically becomes less noticeable over time.
Read more about siding appearance