Building Envelope Project Update

    • Prince George
  • September 10, 2026

Current Updates 

Stay informed with regular updates as construction progresses. We’ll keep you posted on project milestones, potential disruptions, and other important details.

Building envelope work continues across the Prince George Campus. Current activities include window replacement, landscaping, insulation, siding and panel installation, exterior painting, perimeter lighting, canopy work, and other exterior finishing.

Work is taking place in the 100, 200, 300, 400, and 700 Blocks. Through September, crews will continue work on the 300 Block windows and canopy, exterior finishes in several areas, and landscaping preparation around campus.

Accessible parking near the Main Entrance has been relocated until further notice to the crosswalk ramp, and a detour is in place for those walking from the east side.

Check the full map to see how campus blocks are connected and where work is taking place.

Expected Impacts

🔊 Noise: Construction noise is expected from window replacement, exterior wall work, canopy installation, stair work, siding installation, and metal framing. Increased noise is expected in the 300 Block North later in September during installation of clips and metal framing.

🚧 Access: Temporary barriers and localized detours may be in place near active work areas. Please follow posted signage and use alternate routes where required.

🪟 Window Replacement: Window replacement continues in the 300 Block North. Work is scheduled in several first-, second-, and third-floor areas through mid-September.

👷 Construction Activity: Landscaping, insulation, siding, perimeter lighting, painting, canopy work, and exterior finishing will continue across several areas of campus.

Please follow posted signage and allow extra time when travelling through construction areas.

Upcoming Activities

September 7–13

100 Block

  • Prepare grades for landscaping 

200 Block

  • Install insulation and trim
  • Continue exterior siding and panel work

300 Block South

  • Prepare for the new courtyard canopy near the gym

300 Block

  • Window replacement continues
  • Paint stucco wall near the bridge 
  • Paint the loading dock area 

300 Block North

  • Repair air barrier
  • Install insulation

400 Block

  • Install spray foam insulation in soffits during the weekend
  • Frame soffits for perimeter lighting

700 Block

  • Complete perimeter lighting installation
  • Prepare grades for landscaping 
  • Continue deficiency work
  • Install red exterior panels
  • Continue mechanical penthouse siding

September 14–20

100 Block

  • Continue preparation for landscaping 

200 Block

  • Continue exterior panel installation

300 Block South

  • Continue preparation for the new canopy

300 Block

  • Demolish the existing garbage enclosure near the loading dock

300 Block North

  • Continue insulation installation

400 Block

  • Install spray foam insulation in soffits during the weekend
  • Continue framing soffits for perimeter lighting

700 Block

  • Prepare grades for landscaping 
  • Continue installation of red exterior panels
  • Continue mechanical penthouse siding

September 21–27

200 Block

  • Continue exterior panel installation

300 Block South

  • Install main-floor siding and panels
  • Install new canopy

300 Block

  • Install stair treads

300 Block North

  • Install clips and metal framing 🔊
  • Install trim and siding

400 Block

  • Continue framing soffits for perimeter lighting

700 Block

  • Clean up materials and crates

Main Entrance

  • Tentative scaffold installation for skylight work

September 28–October 4

300 Block South

  • Continue main-floor siding and panel installation

300 Block

  • Continue stair tread installation

300 Block North

  • Continue trim and siding installation

Main Entrance

  • Tentative skylight scaffold installation

About the Project

The Building Envelope Project is designed to enhance the exterior of the Prince George Campus through energy-efficient upgrades, improved sustainability, and long-term infrastructure renewal. These improvements will help create a more comfortable and resilient campus for students, employees, and visitors.

This project is made possible with restricted capital funding by the Ministry of Infrastructure. 

The Building Envelope Project supports CNC’s Strategic Plan (lhulh whuts’odutel’eh – Learning Together) under Priority 3.5: Rejuvenate College Infrastructure. Specifically, it supports objectives 3.5.1 through 3.5.4 by upgrading campus infrastructure, revitalizing learning spaces, improving sustainability, and helping reduce the college’s overall carbon footprint.

Key Highlights of the Project: 

  • Energy-efficient building upgrades
  • Modernized campus exterior
  • Improved long-term durability and sustainability

Project Timeline

  • March 2025: Project mobilization and site preparation
  • May 2025: Construction begins
  • Summer–Fall 2025: Demolition and exterior renewal work
  • Winter 2025–26: Interior and exterior finishing activities
  • Spring 2026: Major exterior upgrades continue across campus
  • Estimated Completion: May 2027

Impact on Campus

We are committed to minimizing disruptions during construction. Updates will be provided regarding:

  • Campus accessibility
  • Temporary disruptions and detours
  • Changes to parking, entrances, and pedestrian routes

Our team is focused on ensuring that the impact on your daily experience is as minimal as possible. 

Building Envelope Project FAQ

Why does some of the new siding look wavy?

Some members of the campus community may notice slight waviness or “ripples” in portions of the new metal siding. This effect, known as oil canning, is a common characteristic of flat metal siding and is widely recognized across the construction industry. 

Oil canning is a visual effect only. It does not affect the strength, safety, durability, or weather protection of the building. The project team continues to monitor installation quality to ensure the work meets project requirements and industry standards. 

The effect is often more noticeable in certain lighting and typically becomes less noticeable over time. 

Read more about siding appearance

Questions?

construction@cnc.bc.ca

Your voice is important

Would you like for your story to be featured on the CNC site? Get in touch!
Share your story with us

Contact Media Relations media@cnc.bc.ca