Current Updates
Stay informed with regular updates as construction progresses. We’ll keep you posted on project milestones, potential disruptions, and other important details.
Building envelope work continues across the Prince George Campus. Current work includes window replacement, landscaping, insulation, siding and panel installation, exterior painting, lighting, and finishing work.
Work is taking place in the 100, 200, 300, 400, and 700 Blocks. In the coming weeks, crews will continue exterior upgrades while completing work around areas being used for the start of the fall term.
Accessible parking near the Main Entrance has been relocated until further notice to the crosswalk ramp, and a detour is in place for those walking from the east side.
Check the full map to see how campus blocks are connected and where work is taking place.
Expected Impacts
🔊 Noise: Construction noise is expected from window replacement, exterior wall work, siding installation, and metal framing. Increased noise is expected when clips and metal framing are installed in the 300 Block North later in September.
🚧 Access: Temporary barriers and localized detours may be in place near active work areas. Please follow posted signage and use alternate routes where required.
🪟 Window Replacement: Window replacement continues in the 300 Block through September. Work will move through scheduled rooms and bays, including areas on the first, second, and third floors.
👷 Construction Activity: Landscaping, insulation, siding, exterior panels, perimeter lighting, painting, and finishing work will continue across several areas of campus.
Please follow posted signage and allow extra time when travelling through construction areas.
Upcoming Activities
August 31–September 6
Site-wide
- Prepare campus for the start of the school year
100 Block
200 Block
- Install insulation, trims, and siding
300 Block South
- Prepare for the new canopy at the remaining entrance
300 Block
- Paint the loading dock area
- Install insulation
300 Block North
300 Block Window Replacement 🪟
- August 31: 2-309
- August 31–September 1: 2-309 to 2-309A
- September 1–2: 3-365-D to 3-365
- September 2–3: 3-365 to 3-365C
- September 3–4: 3-376 to 3-374A
400 Block
- Install DensGlass wall panels
700 Block
- Install perimeter lighting
- Prepare landscaping
- Complete deficiency work
- Install red siding panels
September 7–13
200 Block
- Continue insulation, trim, and siding installation
300 Block
- Paint stucco on the second floor near the bridge
- Paint the loading dock area
- Continue insulation installation
300 Block Window Replacement 🪟
- September 8–9: 3-374A to 3-373
- September 9–10: 3-372 to 3-371
- September 11: 1-315, 1-345, 1-346 and 1-314
The contractor's window schedule identifies these as the next areas following the Labour Day weekend.
400 Block
- Frame soffits for perimeter lighting
700 Block
- Continue perimeter lighting installation
- Prepare landscaping
- Complete deficiency work
- Install red siding panels
- Install siding on the mechanical penthouse
September 14–20
200 Block
- Continue siding installation
300 Block Window Replacement 🪟
- September 14: 1-315, 1-345, 1-346 and 1-314
- September 15–16: 1-311, 1-350 and 1-339
- September 17–18: 2-510
These are the final areas shown on the current detailed window schedule.
400 Block
- Continue framing soffits for perimeter lighting
700 Block
- Complete deficiency work
- Continue red siding panel installation
- Continue siding on the mechanical penthouse
September 21–27
300 Block South
- Install main-floor siding
300 Block North
- Install clips and metal framing 🔊
- Install stair treads near the bridge
300 Block
700 Block
- Continue cleanup of materials and crates
About the Project
The Building Envelope Project is designed to enhance the exterior of the Prince George Campus through energy-efficient upgrades, improved sustainability, and long-term infrastructure renewal. These improvements will help create a more comfortable and resilient campus for students, employees, and visitors.
This project is made possible with restricted capital funding by the Ministry of Infrastructure.
The Building Envelope Project supports CNC’s Strategic Plan (lhulh whuts’odutel’eh – Learning Together) under Priority 3.5: Rejuvenate College Infrastructure. Specifically, it supports objectives 3.5.1 through 3.5.4 by upgrading campus infrastructure, revitalizing learning spaces, improving sustainability, and helping reduce the college’s overall carbon footprint.
Key Highlights of the Project:
- Energy-efficient building upgrades
- Modernized campus exterior
- Improved long-term durability and sustainability
Project Timeline
- March 2025: Project mobilization and site preparation
- May 2025: Construction begins
- Summer–Fall 2025: Demolition and exterior renewal work
- Winter 2025–26: Interior and exterior finishing activities
- Spring 2026: Major exterior upgrades continue across campus
- Estimated Completion: May 2027
Impact on Campus
We are committed to minimizing disruptions during construction. Updates will be provided regarding:
- Campus accessibility
- Temporary disruptions and detours
- Changes to parking, entrances, and pedestrian routes
Our team is focused on ensuring that the impact on your daily experience is as minimal as possible.
Building Envelope Project FAQ
Why does some of the new siding look wavy?
Some members of the campus community may notice slight waviness or “ripples” in portions of the new metal siding. This effect, known as oil canning, is a common characteristic of flat metal siding and is widely recognized across the construction industry.
Oil canning is a visual effect only. It does not affect the strength, safety, durability, or weather protection of the building. The project team continues to monitor installation quality to ensure the work meets project requirements and industry standards.
The effect is often more noticeable in certain lighting and typically becomes less noticeable over time.
Read more about siding appearance