Current Updates
Stay informed with regular updates as construction progresses. We’ll keep you posted on project milestones, potential disruptions, and other important details.
Building envelope work continues across the Prince George Campus. Current work includes window replacement, landscaping, exterior wall upgrades, panel installation, painting, lighting, and finishing work.
Work is taking place in the 100, 200, 300, 400, and 700 Blocks, with additional activities planned through September.
Accessible parking near the Main Entrance has been relocated until further notice to the crosswalk ramp, and a detour is in place for those walking from the east side.
Check the full map to see how campus blocks are connected and where work is taking place.
Expected Impacts
🔊 Noise: Construction noise is expected from window replacement, exterior wall work, stair installation, panel installation, and other active construction activities.
🚧 Access: Temporary barriers and localized detours may be in place near active work areas. Please follow posted signage and use alternate routes where required.
🪟 Window Replacement: Window replacement continues in the 300 Block West and will move through additional areas of the 300 Block into September. Occupants in affected areas should expect construction activity near scheduled rooms.
👷 Construction Activity: Landscaping, insulation, exterior panels, strip lighting, painting, and finishing work continue across several areas of campus. Crews are also preparing the site for the start of the school year.
Please follow posted signage and allow extra time when travelling through construction areas.
Upcoming Activities
August 24–30
100 Block
200 Block
- Install insulation
- Install trim
- Install finish panels
300 Block
- Install windows in the 300 Block West 🪟
- Paint stucco wall
300 Block Window Replacement | Night Shift (4:00pm – 1:00am)
- August 24–25: 3-339 to 3-336, Bay 8
- August 24: 3-336, Bay 7
- August 25–26: 2-312 to 2-310, Bay 10
- August 26–27: 2-310 to 2-309, Bay 11
- August 27–28: 2-309, Bay 12
- August 28: 2-309, Bay 13
300 Block North
- Install insulation clips and girts
- Install stairs and treads
400 Block
- Install DensGlass wall panels
- Frame and insulate exterior wall above windows
- Continue exterior wall work
700 Block
- Install strip lighting
- Prepare grades for sod
- Complete deficiency work
August 31–September 6
Campus-wide
- Prepare the site for the start of the school year
100 Block
- Continue preparation for sod
200 Block
- Continue trim installation
- Continue finish panel installation
300 Block
- Continue window replacement 🪟
- Paint the loading dock area
300 Block Window Replacement | Night Shift (4:00pm – 1:00am)
- August 31: 2-309, Bay 13
- August 31–September 1: 2-309 to 2-309A, Bay 14
- September 1–2: 3-365-D to 3-365, Bay 15
- September 2–3: 3-365 to 3-365C, Bay 16
- September 3–4: 3-376 to 3-374A, Bay 17
300 Block North
- Repair air barrier
- Continue insulation work
400 Block
- Frame soffits for exterior strip lighting
700 Block
- Continue landscaping and sod preparation
- Continue deficiency work
September 7–13
200 Block
- Continue finish panel installation
300 Block
- Continue scheduled window replacement 🪟
300 Block Window Replacement | Night Shift (4:00pm – 1:00am)
- September 8–9: 3-374A to 3-373, Bay 18
- September 9–10: 3-372 to 3-371, Bay 19
- September 11: 1-315, 1-345, 1-346 and 1-314
300 Block North
400 Block
- Continue soffit framing for exterior strip lighting
700 Block
- Install ACM panels
- Continue mechanical penthouse work
September 14–20
300 Block Window Replacement | Night Shift (4:00pm – 1:00am)
- September 14: 1-315, 1-345, 1-346 and 1-314
- September 15–16: 1-311, 1-350 and 1-339
- September 17–18: 2-510
700 Block
- Continue ACM panel installation
- Continue mechanical penthouse work
About the Project
The Building Envelope Project is designed to enhance the exterior of the Prince George Campus through energy-efficient upgrades, improved sustainability, and long-term infrastructure renewal. These improvements will help create a more comfortable and resilient campus for students, employees, and visitors.
This project is made possible with restricted capital funding by the Ministry of Infrastructure.
The Building Envelope Project supports CNC’s Strategic Plan (lhulh whuts’odutel’eh – Learning Together) under Priority 3.5: Rejuvenate College Infrastructure. Specifically, it supports objectives 3.5.1 through 3.5.4 by upgrading campus infrastructure, revitalizing learning spaces, improving sustainability, and helping reduce the college’s overall carbon footprint.
Key Highlights of the Project:
- Energy-efficient building upgrades
- Modernized campus exterior
- Improved long-term durability and sustainability
Project Timeline
- March 2025: Project mobilization and site preparation
- May 2025: Construction begins
- Summer–Fall 2025: Demolition and exterior renewal work
- Winter 2025–26: Interior and exterior finishing activities
- Spring 2026: Major exterior upgrades continue across campus
- Estimated Completion: May 2027
Impact on Campus
We are committed to minimizing disruptions during construction. Updates will be provided regarding:
- Campus accessibility
- Temporary disruptions and detours
- Changes to parking, entrances, and pedestrian routes
Our team is focused on ensuring that the impact on your daily experience is as minimal as possible.
Building Envelope Project FAQ
Why does some of the new siding look wavy?
Some members of the campus community may notice slight waviness or “ripples” in portions of the new metal siding. This effect, known as oil canning, is a common characteristic of flat metal siding and is widely recognized across the construction industry.
Oil canning is a visual effect only. It does not affect the strength, safety, durability, or weather protection of the building. The project team continues to monitor installation quality to ensure the work meets project requirements and industry standards.
The effect is often more noticeable in certain lighting and typically becomes less noticeable over time.
Read more about siding appearance
Questions?
construction@cnc.bc.ca