Current Updates 

Stay informed with regular updates as construction progresses. We’ll keep you posted on project milestones, potential disruptions, and other important details.

Building envelope work continues across several areas of campus through mid-August. Crews are progressing with window installation, exterior wall systems, siding, insulation, and finishing work while preparing additional areas for the next phase of construction.

Major activities include continued window replacement in the 200 Block, exterior wall upgrades on the 300 and 400 Blocks, landscaping preparation around the 100 Block, and ongoing finishing work on the 500 and 700 Blocks.

Accessible parking near the Main Entrance has been relocated until further notice to the crosswalk ramp, and a detour is in place for those walking from the east side.

Check the full map to see how campus blocks are connected and where work is taking place.

Expected Impacts:

🔊 Noise: Elevated noise is expected from window installation in the 200 Block, stair landing removal in the 300 Block North, stucco removal in the 400 Block, and ongoing exterior wall installation and framing work.

🚧 Access: The 300 Block main entrance remains partially closed while entrance canopy and panel work continues. Temporary barriers, fencing changes, and localized detours may be in place near active work areas.

🪟 Window Replacement: Window installation continues in the 200 Block. Preparation work for window replacement is underway in the 300 Block connector, with window installation on the west side of the 300 Block beginning in early August. Occupants in affected areas will be notified before work begins.

👷 Construction Activity: Landscaping preparation continues around the 100 Block. Exterior wall installation, insulation, siding, painting, and material deliveries continue across the 300, 400, 500, and 700 Blocks. Equipment and construction vehicles will remain active throughout the site.

 

Please follow posted signage and allow extra time when travelling through construction areas.

Upcoming Activities

July 20 - 26

Sitewide

  • Site cleanup and fence removal 🚧

100 Block

  • Prepare ground for new sod 

200 Block

  • Fiberglass window installation 🪟

300 Block South

  • Install ground floor panels
  • Install insulation

300 Block North

  • Remove existing stair landing (Thursday to Saturday) 🔊
  • Prepare windows in the connector between the 300 and 400/500 Blocks 🪟
  • Insulation installation

300 Block West

  • Install metal clips and framing
  • Insulation installation

400 Block

  • Stucco removal 🔊
  • Install air barrier
  • Install metal clips and framing

500 Block

  • Exterior painting 

700 Block

  • Paint second-floor exit handrails

200 Block Window Schedule

  • July 20–21: Room 3-236 (NRFT Prep Lab)
  • July 21-22: Room 3-238 (MLTS Lab)

July 27 - August 2

200 Block

  • Install insulation and trim

300 Block South

  • Concrete work at entrance canopies 🚧
  • Install ground floor panels
  • Install insulation

300 Block North

  • Install metal clips and framing
  • Insulation installation

300 Block West

  • Install metal clips and framing
  • Insulation installation

400 Block

  • Install air barrier
  • Install DensGlass wall panels
  • Frame and insulate new exterior wall above windows
  • Frame soffits for strip lighting

700 Block

  • Paint second-floor exit handrails
  • Install mechanical penthouse siding

August 3 – 9

200 Block

  • Continue insulation and trim installation

300 Block South

  • Install ground floor panels
  • Install siding at the main entrance

300 Block West

  • Window installation 🪟

300 Block North

  • Insulation installation

400 Block

  • Install DensGlass wall panels
  • Frame and insulate new exterior wall above windows
  • Frame soffits for strip lighting

700 Block

  • Install red siding panels
  • Install mechanical penthouse siding

August 10 - 16

200 Block

  • Begin siding installation

300 Block South

  • Continue installing ground floor panels

300 Block North

  • Install stairs and treads 🚧

700 Block

  • Install exterior perimeter lighting
  • Install red siding panels
  • Install mechanical penthouse siding

About the Project

The Building Envelope Project is designed to enhance the exterior of the Prince George Campus through energy-efficient upgrades, improved sustainability, and long-term infrastructure renewal. These improvements will help create a more comfortable and resilient campus for students, employees, and visitors.

This project is made possible with restricted capital funding by the Ministry of Infrastructure. 

The Building Envelope Project supports CNC’s Strategic Plan (lhulh whuts’odutel’eh – Learning Together) under Priority 3.5: Rejuvenate College Infrastructure. Specifically, it supports objectives 3.5.1 through 3.5.4 by upgrading campus infrastructure, revitalizing learning spaces, improving sustainability, and helping reduce the college’s overall carbon footprint.

Key Highlights of the Project: 

  • Energy-efficient building upgrades
  • Modernized campus exterior
  • Improved long-term durability and sustainability

Project Timeline

  • March 2025: Project mobilization and site preparation
  • May 2025: Construction begins
  • Summer–Fall 2025: Demolition and exterior renewal work
  • Winter 2025–26: Interior and exterior finishing activities
  • Spring 2026: Major exterior upgrades continue across campus
  • Estimated Completion: May 2027

Impact on Campus

We are committed to minimizing disruptions during construction. Updates will be provided regarding:

  • Campus accessibility
  • Temporary disruptions and detours
  • Changes to parking, entrances, and pedestrian routes

Our team is focused on ensuring that the impact on your daily experience is as minimal as possible. 

Building Envelope Project FAQ

Why does some of the new siding look wavy?

Some members of the campus community may notice slight waviness or “ripples” in portions of the new metal siding. This effect, known as oil canning, is a common characteristic of flat metal siding and is widely recognized across the construction industry. 

Oil canning is a visual effect only. It does not affect the strength, safety, durability, or weather protection of the building. The project team continues to monitor installation quality to ensure the work meets project requirements and industry standards. 

The effect is often more noticeable in certain lighting and typically becomes less noticeable over time. 

Read more about siding appearance

Questions?

construction@cnc.bc.ca

Your voice is important

Would you like for your story to be featured on the CNC site? Get in touch!
Share your story with us

Contact Media Relations media@cnc.bc.ca