Current Updates
Stay informed with regular updates as construction progresses. We’ll keep you posted on project milestones, potential disruptions, and other important details.
Building envelope work continues across the Prince George Campus through early August. Current work includes window replacement, exterior wall upgrades, siding installation, landscaping, painting, roof work, and exterior finishing.
Work is taking place in the 100, 200, 300, 400, 500, and 700 Blocks.
Accessible parking near the Main Entrance has been relocated until further notice to the crosswalk ramp, and a detour is in place for those walking from the east side.
Check the full map to see how campus blocks are connected and where work is taking place.
Expected Impacts:
🔊 Noise: Elevated noise levels may occur from window replacement, exterior wall installation, and stucco removal. Removing the existing stair landing in the 300 Block North and predrilling for window replacement in the 200 Block may create elevated noise during scheduled work.
🚧 Access: The 300 Block main entrance remains partially closed while door installation continues. Temporary barriers, fencing changes, and localized detours may also be in place as work progresses.
🚪 Window Replacement: Window replacement continues on the north side of the 200 Block and will begin on the west side of the 300 Block later this month. Occupants in affected areas will be notified before work begins.
👷 Construction Activity: Equipment movement, material deliveries, landscaping, and exterior finishing continue throughout active work zones.
Please follow posted signage and allow extra time when travelling through construction areas.
Upcoming Activities
July 13 – 19
Sitewide
- Fence removal and site cleanup 🚧
100 Block
Prepare ground for new sod
200 Block
- Fiberglass window installation 🚪
300 Block South
- Concrete work at entrance canopies 🔊
- Stairwell doors and glazing installation 🚪
- Main entrance door installation (partially closed) 🚧
300 Block North
- Remove existing stair landing (weekend work – elevated noise) 🔊
- Exterior wall framing
- Insulation installation
300 Block West
- Exterior wall framing
- Insulation installation
400 Block
- Stucco removal near the daycare (weekend work) 🔊
- Air barrier installation
- Exterior wall framing
- Exterior wall panel installation
- Frame and insulate exterior wall above windows
500 Block
700 Block
- Perimeter soffit lighting
- Flashing and beauty cap installation
- Vestibule door replacement 🚪
- Ground floor interior corner siding
200 Block Window Schedule
- July 13–14: Room 2-243 (Psychology)
- July 14–15: Room 2-242 (Faculty Offices)
- July 16-17: Room 3-234 (NRFT Lab)
July 20 - 26
Sitewide
100 Block
- Prepare ground for new sod
200 Block
- Fiberglass window installation 🚪
300 Block South
- Main entrance door installation (partially closed) 🚧
300 Block North
- Prepare crossover windows between the 300 and 400/500 Blocks
- Exterior wall framing
- Insulation installation
300 Block West
- Exterior wall framing
- Insulation installation
400 Block
- Air barrier installation
- Exterior wall framing
- Exterior wall panel installation
- Frame and insulate exterior wall above windows
700 Block
- Paint handrails at second-floor exits
200 Block Window Schedule
- July 20–21: Room 3-236 (NRFT Prep Lab)
- July 21-22: Room 3-238 (MLTS Lab)
July 27 - August 2
200 Block
- Building-wide insulation and trim installation
300 Block South
- Concrete work at entrance canopies 🔊
- Main floor panel installation
300 Block North
- Exterior wall framing
- Insulation installation
300 Block West
- Window installation 🚪
- Exterior wall framing
- Insulation installation
400 Block
- Stucco removal near the daycare 🔊
- Air barrier installation
- Exterior wall framing
- Soffit framing for strip lighting
700 Block
- Clean up materials and crates 🚧
- Mechanical penthouse siding
August 3 – 9
300 Block South
- Install siding at the main entrance
300 Block North
- Install new stairs and treads
300 Block West
700 Block
- Install red siding panels
About the Project
The Building Envelope Project is designed to enhance the exterior of the Prince George Campus through energy-efficient upgrades, improved sustainability, and long-term infrastructure renewal. These improvements will help create a more comfortable and resilient campus for students, employees, and visitors.
This project is made possible with restricted capital funding by the Ministry of Infrastructure.
The Building Envelope Project supports CNC’s Strategic Plan (lhulh whuts’odutel’eh – Learning Together) under Priority 3.5: Rejuvenate College Infrastructure. Specifically, it supports objectives 3.5.1 through 3.5.4 by upgrading campus infrastructure, revitalizing learning spaces, improving sustainability, and helping reduce the college’s overall carbon footprint.
Key Highlights of the Project:
- Energy-efficient building upgrades
- Modernized campus exterior
- Improved long-term durability and sustainability
Project Timeline
- March 2025: Project mobilization and site preparation
- May 2025: Construction begins
- Summer–Fall 2025: Demolition and exterior renewal work
- Winter 2025–26: Interior and exterior finishing activities
- Spring 2026: Major exterior upgrades continue across campus
- Estimated Completion: May 2027
Impact on Campus
We are committed to minimizing disruptions during construction. Updates will be provided regarding:
- Campus accessibility
- Temporary disruptions and detours
- Changes to parking, entrances, and pedestrian routes
Our team is focused on ensuring that the impact on your daily experience is as minimal as possible.
Building Envelope Project FAQ
Why does some of the new siding look wavy?
Some members of the campus community may notice slight waviness or “ripples” in portions of the new metal siding. This effect, known as oil canning, is a common characteristic of flat metal siding and is widely recognized across the construction industry.
Oil canning is a visual effect only. It does not affect the strength, safety, durability, or weather protection of the building. The project team continues to monitor installation quality to ensure the work meets project requirements and industry standards.
The effect is often more noticeable in certain lighting and typically becomes less noticeable over time.
Read more about siding appearance
Questions?
construction@cnc.bc.ca