Building Envelope Project Update

    • Prince George
  • June 11, 2026

Current Updates 

Stay informed with regular updates as construction progresses. We’ll keep you posted on project milestones, potential disruptions, and other important details.

 

Building envelope upgrades continue across the Prince George Campus throughout June. Current work includes roofing, concrete repairs, window and door installation, glazing, exterior lighting, landscaping, weatherproofing, painting, siding installation, and cleanup activities.

Work is underway in the 100, 200, 300, 400, 500, and 700 Blocks, including entrances, stairwells, canopies, exterior walls, and courtyard areas.

Accessible parking near the Main Entrance has been relocated until further notice to the crosswalk ramp, and a detour is in place for those walking from the east side.

The East Entrance remains closed, the Main Entrance is partially closed, and the 300 Block 2nd-floor exit to the Trades buildings is closed for an hour in the afternoon of Friday, June 12th.

Check the full map to see how campus blocks are connected and where work is taking place.

Expected Impacts:

🔊 Noise: Elevated noise levels from concrete work, stucco removal, roofing activities, metal framing installation, and exterior finishing work.

🚧 Access: Temporary barriers, detours, and intermittent entrance impacts remain in place. The East Entrance remains closed while work continues.

⚠️ Friday Closure: The bridge connecting the main campus (300 Block 2nd Floor) to Canfor Tech Building will be temporarily closed for approximately one hour on Friday afternoon to allow for concrete pouring. Please follow posted signage and use alternate routes.

👷 Work Zones: Construction activity, equipment movement, material staging, landscaping repairs, and cleanup activities continue around active work areas.

Upcoming Activities

June 8 – 14

Sitewide

  • Fence removal and cleanup activities 🚧
  • Sidewalk replacement work 🔊

100 Block

  • Cleanup of materials and crates 
  • Landscaping repairs and lawn preparation 

200 Block

  • Installation of parapet cap 
  • Installation of clips and metal framing system 🔊

300 Block South

  • First-floor interior finishes 
  • Concrete work at canopies 🔊
  • Installation of missing windows 
  • Main floor panel installation 
  • Canopy wood-look finishes 

300 Block North

  • Slab preparation and concrete pouring 🔊

300 Block West

  • Waterproof membrane application 

400 Block

  • Stucco removal 🔊
  • DensGlass installation 🔊
  • Strip lighting framing 

500 Block

  • Exterior painting 
  • Exposed rebar repairs 🔊
  • Vine removal 

700 Block

  • Interior cleaning 
  • Roof cap flashing installation 🔊
  • Door and glazing installation 
  • Vestibule door installation 
  • Flashing and beauty cap installation 
  • Strip lighting installation 
  • Main entrance wood-look siding 
  • Ground floor wood-look siding
  • Mechanical penthouse siding 
  • Landscaping repairs 

Special Access Impact

  • Friday, June 12 afternoon: Bridge connecting the main campus (300 Block 2nd floor) and Canfor Tech will be closed for approximately one hour during concrete pouring. 🚧

June 15 – 21

Sitewide

  • Continued fence removal and cleanup 🚧
  • Sidewalk replacement work 🔊

200 Block

  • Installation of clips and metal framing system 🔊

300 Block South

  • Interior finishes continue 
  • Main floor panel installation 
  • Canopy wood-look finishes 

300 Block North

  • Concrete and foundation work continues 🔊

300 Block West

  • Waterproof membrane application 

400 Block

  • DensGlass installation 🔊
  • Strip lighting framing 

500 Block

  • Exterior painting 

700 Block

  • Roof cap flashing installation 🔊
  • Door and glazing installation 
  • Vestibule door installation 
  • Main entrance wood-look siding 
  • Ground floor wood-look siding 
  • Mechanical penthouse siding 

June 22 – 28

Sitewide

  • Continued cleanup and fence removal 🚧

200 Block

  • Metal framing and exterior wall work 

300 Block South

  • Exterior finishing work 

300 Block North

  • Exterior wall and weatherproofing work 

300 Block West

  • Waterproof membrane and wall assembly work 

400 Block

  • DensGlass and exterior panel installation 
  • Strip lighting framing 

700 Block

  • Wood-look siding installation 
  • Mechanical penthouse finishing work 
  • Final glazing and exterior finishing activities 

Project Wide

  • Ongoing cleanup, landscaping restoration, and completion work 

About the Project 

The Building Envelope Project is designed to enhance the exterior of the Prince George campus with energy-efficient upgrades, a modernized aesthetic, and a focus on long-term sustainability. These improvements will provide a more comfortable, energy-efficient space for everyone at CNC while maintaining our facilities’ resilience well into the future.

This project is made possible with restricted capital funding by the Ministry of Infrastructure. 

The Building Envelope Project aligns with CNC’s Strategic Plan (lhulh whuts’odutel’eh – Learning Together) under Priority 3.5: Rejuvenate College Infrastructure. Specifically, it supports objectives 3.5.1 through 3.5.4 by upgrading campus infrastructure, revitalizing learning spaces, improving sustainability, and helping reduce the college’s overall carbon footprint.

Key Highlights of the Project: 

  • Energy-efficient upgrades for better sustainability.
  • A modernized campus exterior to reflect our commitment to innovation.
  • Long-term durability to ensure the campus remains functional and eco-friendly for years to come.  

Project Timeline

  • March 2025: Pre-construction preparations and site setup begin.
  • April 11: Pre-construction phase
  • April 25: Transition to demolition stage.
  • May 2025: Official construction begins.
  • May 9, 2025: Demolition work on the 100 Block started
  • June 8, 2025: 100 Block demolition work largely complete. Demolition work on the 700 Block started.
  • June 15, 2025: Demolition work on the east and south side of the 700 Block continues.
  • July 2, 2025: Installation of initial building envelope components at the east and south side of the 700 Block started.
  • August 11, 2025: Roof work, brick façade and wall stucco removal on the 700 Block started
  • August 18, 2025: Penthouse demolition and landscaping work on the 700 Block started
  • September 4, 2025: Elevated walkway work on the 300 Block started
  • September 8, 2025: Window replacement work on the 100 Block started. Moisture shield barrier installation on 100 Block started.
  • October 14, 2025: Sidewalk and foundation removal at the west entrance of the 500 Block for stair replacement started.
  • October 20, 2025: 100 Block interior window trims work start. 700 Block brick façade almost done.
  • November 25, 2025: 500 block stairs installed. Weight room and 2nd floor open. Slight detour in West Entrance lifted
  • November 26, 2025: 700 block, 1st floor window replacement
  • December 22, 2025: Water shield installation done
  • January 2026:
    • Interior and exterior finishing activities continue across active blocks
    • Ongoing window replacement and detailing work on the 700 Block
  • February 2026:
    • Exterior envelope work expands across the 100 and 700 Blocks
    • Continued preparation for upcoming roofing, panel, and entrance upgrades
    • Interior finishing and staging activities continue in occupied areas
  • March 2026:
    • Early prep work begins for spring exterior construction activities
    • Roofing, panel systems, and exterior access planning continue
  • April 2026:
    • Major exterior building envelope work ramps up across the 100, 300, 400, and 700 Blocks
    • Window sealing, siding installation, roofing, and exterior finishes underway
  • May 6-8, 2026: Concrete fin removal above the loading dock
  • Duration: Approximately 2 years 
  • Completion Date: May 2027 (estimated) 

Impact on Campus

We are committed to minimizing disruptions during construction. While work is taking place, we will keep staff, students and visitors informed about: 

  • Campus accessibility 
  • Potential disruptions 
  • Changes to parking and entrances 

Our team is focused on ensuring that the impact on your daily experience is as minimal as possible. 

Your voice is important

Would you like for your story to be featured on the CNC site? Get in touch!
Share your story with us

Contact Media Relations media@cnc.bc.ca