Building Envelope Project Update

    • Prince George
  • June 11, 2026

Current Updates 

Stay informed with regular updates as construction progresses. We’ll keep you posted on project milestones, potential disruptions, and other important details.

Building envelope work continues across the Prince George Campus through mid-July. Current work includes window installation, concrete work, exterior wall upgrades, siding installation, landscaping, painting, roof work, sidewalk replacement, and exterior finishing.

Work is taking place in the 100, 200, 300, 400, 500, and 700 Blocks.

Accessible parking near the Main Entrance has been relocated until further notice to the crosswalk ramp, and a detour is in place for those walking from the east side.

Check the full map to see how campus blocks are connected and where work is taking place.

Expected Impacts:

🔊 Noise: Elevated noise levels may occur from sidewalk replacement, concrete work, stucco removal, and exterior wall installation.

🚧 Access: Temporary barriers, fencing changes, and localized detours may be in place as work areas change.

👷 Construction Activity: Equipment movement, landscaping work, material deliveries, and exterior finishing continue throughout active work zones.

Please follow posted signage and allow extra time when travelling through construction areas.

Upcoming Activities

June 22 – 28

Sitewide

  • Fence removal and cleanup 🚧
  • Sidewalk replacement (100 and 700 Blocks) 🔊

100 Block

  • Prepare ground for new sod 

200 Block

  • Fiberglass window installation 
  • Parapet cap installation 

300 Block South

  • Concrete work at canopies 🔊

300 Block North

  • Saw cutting concrete 🔊
  • Apply primer to concrete edges 

400 Block

  • Stucco removal 🔊

500 Block

  • Exterior painting 

700 Block

  • Site cleanup 
  • Window flashing installation 
  • Vestibule door installation 
  • Main entrance wood-look siding 
  • Mechanical penthouse siding

June 29 – July 5

Sitewide

  • Fence removal and cleanup 🚧
  • Sidewalk replacement (100 and 700 Blocks) 🔊

100 Block

  • Prepare ground for new sod 

200 Block

  • Fiberglass window installation 
  • Parapet cap installation 
  • Insulation installation 

300 Block South

  • Main floor panel installation 
  • Canopy wood-look finishes

300 Block North

  • Exterior wall framing 
  • Insulation installation 

300 Block West

  • Exterior wall framing 
  • Waterproof membrane application 

400 Block

  • Exterior wall installation 
  • Strip lighting framing 

500 Block

  • Exterior painting 

700 Block

  • Window flashing installation 
  • Stairwell doors and glazing 
  • Strip lighting 
  • Mechanical penthouse siding 

July 6 – 12

100 Block

  • Prepare ground for new sod 

200 Block

  • Fiberglass window installation 
  • Insulation installation 

300 Block North

  • Exterior wall framing 
  • Insulation installation 

300 Block West

  • Exterior wall framing 

400 Block

  • Exterior wall installation 
  • Strip lighting framing 

500 Block

  • Exterior painting 

700 Block

  • Window flashing installation 
  • Stairwell doors and glazing 
  • Strip lighting 
  • Main entrance wood-look siding 
  • Mechanical penthouse siding 

July 13 – 19

100 Block

  • Prepare ground for new sod 

200 Block

  • Fiberglass window installation 
  • Insulation installation 

300 Block North

  • Exterior wall framing 
  • Insulation installation 

300 Block West

  • Exterior wall framing 

400 Block

  • Stucco removal 🔊
  • Exterior wall installation 
  • Strip lighting framing 

500 Block

  • Exterior painting 

700 Block

  • Mechanical penthouse siding 

About the Project

The Building Envelope Project is designed to enhance the exterior of the Prince George Campus through energy-efficient upgrades, improved sustainability, and long-term infrastructure renewal. These improvements will help create a more comfortable and resilient campus for students, employees, and visitors.

This project is made possible with restricted capital funding by the Ministry of Infrastructure. 

The Building Envelope Project supports CNC’s Strategic Plan (lhulh whuts’odutel’eh – Learning Together) under Priority 3.5: Rejuvenate College Infrastructure. Specifically, it supports objectives 3.5.1 through 3.5.4 by upgrading campus infrastructure, revitalizing learning spaces, improving sustainability, and helping reduce the college’s overall carbon footprint.

Key Highlights of the Project: 

  • Energy-efficient building upgrades
  • Modernized campus exterior
  • Improved long-term durability and sustainability

Project Timeline

  • March 2025: Project mobilization and site preparation
  • May 2025: Construction begins
  • Summer–Fall 2025: Demolition and exterior renewal work
  • Winter 2025–26: Interior and exterior finishing activities
  • Spring 2026: Major exterior upgrades continue across campus
  • Estimated Completion: May 2027

Impact on Campus

We are committed to minimizing disruptions during construction. Updates will be provided regarding:

  • Campus accessibility
  • Temporary disruptions and detours
  • Changes to parking, entrances, and pedestrian routes

Our team is focused on ensuring that the impact on your daily experience is as minimal as possible. 

Building Envelope Project FAQ

Why does some of the new siding look wavy?

Some members of the campus community may notice slight waviness or “ripples” in portions of the new metal siding. This effect, known as oil canning, is a common characteristic of flat metal siding and is widely recognized across the construction industry. 

Oil canning is a visual effect only. It does not affect the strength, safety, durability, or weather protection of the building. The project team continues to monitor installation quality to ensure the work meets project requirements and industry standards. 

The effect is often more noticeable in certain lighting and typically becomes less noticeable over time. 

Read more about siding appearance

Questions?

construction@cnc.bc.ca

Your voice is important

Would you like for your story to be featured on the CNC site? Get in touch!
Share your story with us

Contact Media Relations media@cnc.bc.ca