Building Envelope Project Update

    • Prince George
  • May 26, 2026
100725 Update-Image Web BE

Current Updates 

Stay informed with regular updates as construction progresses. We’ll keep you posted on project milestones, potential disruptions, and other important details.

 

Building envelope upgrades continue across multiple areas of the Prince George Campus through May and June.

Current work includes siding installation, roofing, window glazing, landscaping, exterior lighting, stairwell repairs, and cleanup activities in the 100, 300, 400, and 700 Blocks. Crews will also continue work on courtyard areas, exterior entrances, roof flashing, penthouse finishes, and concrete repairs.

 

Accessible parking near the Main Entrance has been relocated until further notice to the crosswalk ramp, and a detour is in place for those walking from the east side.

Check the full map to see how campus blocks are connected and where work is taking place.

Upcoming Activities

May 25 – 31

Site Wide

  • Fence removal and cleanup activities begin

100 Block

  • Cleanup of materials and crates 🚧
  • Penthouse louver and door painting
  • Exterior lighting installation at entrance
  • Landscaping and sprinkler system repairs
  • North side siding completion

300 Block South

  • Window sealing and first floor interior finishes
  • Main floor panel installation 🚧
  • Canopy wood-look finishes

300 Block North

  • Slab preparation and foundation work 🚧
  • Concrete repairs at crossover bridge [300 Block 2nd floor exit closed] 🚧
  • Liquid membrane application and framing work

400 Block

  • Playground dismantling
  • Stucco removal 🔊

700 Block

  • Cleanup activities and penthouse work
  • Roof cap flashing installation
  • Main entrance wood-look siding installation 🚧
  • Ground floor wood-look siding installation
  • Mechanical penthouse siding work
  • Upper soffit finishes
  • Installation of doors and glazing on east side

June 1 – 7

Site Wide

  • Ongoing fence removal and cleanup 🚧

300 Block

  • Stairwell sloped roof work
  • Continued panel and canopy finishes

700 Block

  • Roof flashing installation
  • Exterior flashing and beauty cap installation
  • Door and glazing installation at stairwell

100 Block

  • Continued landscaping and exterior repairs 🚧

June 8 – 14

100 Block

  • Continued siding and exterior finishing work

300 Block North

  • Continued framing and membrane installation

700 Block

  • Continued siding, soffit, and penthouse finishing work
  • Ongoing roof flashing installation

Expected Impacts:

🔊 Noise: Elevated noise levels from roofing, demolition, and exterior finishing work.
🚧 Access: Temporary detours and intermittent entrance impacts may remain in place.
👷Visibility: Continued construction activity, equipment movement, and material staging around active work zones.

Safety Reminder

  • Please follow all posted signage and detour instructions.
  • For your safety, do not enter active construction zones.

About the Project 

The Building Envelope Project is designed to enhance the exterior of the Prince George campus with energy-efficient upgrades, a modernized aesthetic, and a focus on long-term sustainability. These improvements will provide a more comfortable, energy-efficient space for everyone at CNC while maintaining our facilities’ resilience well into the future.

This project is made possible with restricted capital funding by the Ministry of Infrastructure. 

The Building Envelope Project aligns with CNC’s Strategic Plan (lhulh whuts’odutel’eh – Learning Together) under Priority 3.5: Rejuvenate College Infrastructure. Specifically, it supports objectives 3.5.1 through 3.5.4 by upgrading campus infrastructure, revitalizing learning spaces, improving sustainability, and helping reduce the college’s overall carbon footprint.

Key Highlights of the Project: 

  • Energy-efficient upgrades for better sustainability.
  • A modernized campus exterior to reflect our commitment to innovation.
  • Long-term durability to ensure the campus remains functional and eco-friendly for years to come.  

Project Timeline

  • March 2025: Pre-construction preparations and site setup begin.
  • April 11: Pre-construction phase
  • April 25: Transition to demolition stage.
  • May 2025: Official construction begins.
  • May 9, 2025: Demolition work on the 100 Block started
  • June 8, 2025: 100 Block demolition work largely complete. Demolition work on the 700 Block started.
  • June 15, 2025: Demolition work on the east and south side of the 700 Block continues.
  • July 2, 2025: Installation of initial building envelope components at the east and south side of the 700 Block started.
  • August 11, 2025: Roof work, brick façade and wall stucco removal on the 700 Block started
  • August 18, 2025: Penthouse demolition and landscaping work on the 700 Block started
  • September 4, 2025: Elevated walkway work on the 300 Block started
  • September 8, 2025: Window replacement work on the 100 Block started. Moisture shield barrier installation on 100 Block started.
  • October 14, 2025: Sidewalk and foundation removal at the west entrance of the 500 Block for stair replacement started.
  • October 20, 2025: 100 Block interior window trims work start. 700 Block brick façade almost done.
  • November 25, 2025: 500 block stairs installed. Weight room and 2nd floor open. Slight detour in West Entrance lifted
  • November 26, 2025: 700 block, 1st floor window replacement
  • December 22, 2025: Water shield installation done
  • January 2026:
    • Interior and exterior finishing activities continue across active blocks
    • Ongoing window replacement and detailing work on the 700 Block
  • February 2026:
    • Exterior envelope work expands across the 100 and 700 Blocks
    • Continued preparation for upcoming roofing, panel, and entrance upgrades
    • Interior finishing and staging activities continue in occupied areas
  • March 2026:
    • Early prep work begins for spring exterior construction activities
    • Roofing, panel systems, and exterior access planning continue
  • April 2026:
    • Major exterior building envelope work ramps up across the 100, 300, 400, and 700 Blocks
    • Window sealing, siding installation, roofing, and exterior finishes underway
  • May 6-8, 2026: Concrete fin removal above the loading dock
  • Duration: Approximately 2 years 
  • Completion Date: May 2027 (estimated) 

Impact on Campus

We are committed to minimizing disruptions during construction. While work is taking place, we will keep staff, students and visitors informed about: 

  • Campus accessibility 
  • Potential disruptions 
  • Changes to parking and entrances 

Our team is focused on ensuring that the impact on your daily experience is as minimal as possible. 

Your voice is important

Would you like for your story to be featured on the CNC site? Get in touch!
Share your story with us

Contact Media Relations media@cnc.bc.ca