Current Updates
Stay informed with regular updates as construction progresses. We’ll keep you posted on project milestones, potential disruptions, and other important details.
Building envelope work continues through mid April in the 100, 300, and 700 Blocks of the Prince George campus. Crews are completing siding, window sealing, roof work, and exterior finishes. Expect some noise and temporary access changes, especially near the courtyard.
Accessible parking near the Main Entrance has been relocated until further notice to the crosswalk ramp, and a detour is in place for those walking from the east side.
Check the full map to see how campus blocks are connected and where work is taking place.
Upcoming Activities
March 23 - 29
100 Block:
- Sealing around the exterior windows
- Installing siding
300 Block:
- Mechanical roof work
- South:
- Installing flashing, insulation
- Interior finishes (window trims) on the 2nd and 3rd floor
- North:
- Debris clean up
- Installing foundations and preparing area for new concrete slab
700 Block:
- Concrete triangle cutting *NOISY*
- Installation of metal framing on the siding on the east side
- Overheard metal framing beneath the copies for both East and Main entrance
- Install finishing panels on the east side
Windows Work
- Stairwell between corners 300 & 700 Block in the courtyard side
March 30 – April 5
100 Block:
- Sealing around the exterior windows
- Installing siding
- Finishing the siding and flashing with the exception of the black siding on the top of the wall (East side)
300 Block:
- Mechanical roof work
- South:
- Interior finishes (window trims) on the 2nd
- Installing flashing, insulation, and siding panels
- North:
- Debris clean up
- Installing foundations and preparing area for new concrete slab
700 Block:
- Redoing roof over the lounge
- Install finishing panels on the east side
Windows Work
- Stairwell between corners 300 & 700 Block in the courtyard side
April 6 – 12
100 Block
- Finishing the siding and flashing with the exception of the black siding on the top of the wall (North and West side)
300 Block
- South:
- Sealing the exterior windows
- Interior finishes (window trims) on the 1st floor
- Installing flashing, insulation, and siding panels
- North:
- Installing foundations and preparing area for new concrete slab
- Concrete fins removal along the loading dock *NOISY*
- Mechanical roof work
700 Block
- April 8: Removing shipping container
- April 7-17: Installation roof cap flashing
- Installation of exterior doors
- Install finishing panels on the east side
April 13 – 19
300 Block:
- North: Removal of wood soffits
700 Block
- April 7-17: Installation roof cap flashing
- Install finishing panels on the east side
Expected Impacts:
🔊 Noise: Elevated noise levels.
🚧 Access: Temporary alternate routes and partial entrance closures.
👷 Visibility: Ongoing construction activity and visual disruptions in affected areas.
Safety Reminder
- Please follow all posted signage and detour instructions.
- For your safety, do not enter active construction zones.
About the Project
The Building Envelope Project is designed to enhance the exterior of the Prince George campus with energy-efficient upgrades, a modernized aesthetic, and a focus on long-term sustainability. These improvements will provide a more comfortable, energy-efficient space for everyone at CNC while maintaining our facilities’ resilience well into the future.
This project is made possible with restricted capital funding by the Ministry of Infrastructure.
The Building Envelope Project aligns with CNC’s Strategic Plan (lhulh whuts’odutel’eh – Learning Together) under Priority 3.5: Rejuvenate College Infrastructure. Specifically, it supports objectives 3.5.1 through 3.5.4 by upgrading campus infrastructure, revitalizing learning spaces, improving sustainability, and helping reduce the college’s overall carbon footprint.
Key Highlights of the Project:
- Energy-efficient upgrades for better sustainability.
- A modernized campus exterior to reflect our commitment to innovation.
- Long-term durability to ensure the campus remains functional and eco-friendly for years to come.
Project Timeline
- March 2025: Pre-construction preparations and site setup begin.
- April 11: Pre-construction phase
- April 25: Transition to demolition stage.
- May 2025: Official construction begins.
- May 9, 2025: Demolition work on the 100 Block started
- June 8, 2025: 100 Block demolition work largely complete. Demolition work on the 700 Block started.
- June 15, 2025: Demolition work on the east and south side of the 700 Block continues.
- July 2, 2025: Installation of initial building envelope components at the east and south side of the 700 Block started.
- August 11, 2025: Roof work, brick façade and wall stucco removal on the 700 Block started
- August 18, 2025: Penthouse demolition and landscaping work on the 700 Block started
- September 4, 2025: Elevated walkway work on the 300 Block started
- September 8, 2025: Window replacement work on the 100 Block started. Moisture shield barrier installation on 100 Block started.
- October 14, 2025: Sidewalk and foundation removal at the west entrance of the 500 Block for stair replacement started.
- October 20, 2025: 100 Block interior window trims work start. 700 Block brick façade almost done.
- November 25, 2025: 500 block stairs installed. Weight room and 2nd floor open. Slight detour in West Entrance lifted
- November 26, 2025: 700 block, 1st floor window replacement
- December 22, 2025: Water shield installation done
- Duration: Approximately 2 years
- Completion Date: May 2027 (estimated)
Impact on Campus
We are committed to minimizing disruptions during construction. While work is taking place, we will keep staff, students and visitors informed about:
- Campus accessibility
- Potential disruptions
- Changes to parking and entrances
Our team is focused on ensuring that the impact on your daily experience is as minimal as possible.