Current Updates
Stay informed with regular updates as construction progresses. We’ll keep you posted on project milestones, potential disruptions, and other important details.
Building envelope work continues across the Prince George Campus. Current activities include landscaping, siding and trim installation, exterior wall upgrades, canopy and stair work, painting, soffit work, and other exterior finishing.
Work is taking place in the 100, 200, 300, 400, and 700 Blocks, as well as the main courtyard. Through October, crews will continue exterior finishing, landscaping, and siding work, with skylight work at the 700 Block planned later in the month.
Accessible parking near the Main Entrance has been relocated until further notice to the crosswalk ramp, and a detour is in place for those walking from the east side.
Check the full map to see how campus blocks are connected and where work is taking place.
Expected Impacts
🔊 Noise: Increased construction noise is expected in the 300 Block North during installation of metal clips and framing. Noise may also occur during stair, canopy, siding, and other exterior work.
🚧 Access: Temporary barriers and localized detours may be in place near active work areas. Please follow posted signage and use alternate routes where required.
🌱 Landscaping: Landscaping continues around the 100 and 700 Blocks and will move into the main courtyard.
👷 Construction Activity: Exterior siding, trim, painting, canopy work, stair installation, soffit work, landscaping, and other finishing activities will continue across several areas of campus.
Please follow posted signage and allow extra time when travelling through construction areas.
Upcoming Activities
September 21–27
100 Block
- Prepare ground and install sod 🌱
200 Block
300 Block South
- Install wood-look siding on the courtyard side
300 Block North
- Install stair treads
- Install metal clips and framing 🔊 Increased noise expected
- Repair air barrier
- Install insulation
- Install trim and siding
300 Block
- Paint the loading dock area
400 Block
- Paint concrete columns near the daycare and dental areas
- Install spray foam insulation at exterior soffits during the weekend
700 Block
- Clean up materials and work areas
- Prepare ground and install sod 🌱
Main Courtyard
September 28–October 4
200 Block
- Continue trim and siding installation
300 Block South
- Continue wood-look siding installation on the courtyard side
- Install canopy over the courtyard-side entrance
300 Block North
- Demolish the brick garbage enclosure near the loading dock
- Continue stair tread installation
- Continue metal clip and framing installation 🔊 Increased noise expected
- Continue trim and siding installation
400 Block
- Continue painting concrete columns near the daycare and dental areas
- Frame soffits for perimeter lighting
700 Block
- Tentative scaffold installation for upcoming skylight work
Main Courtyard
October 5–11
200 Block
- Continue trim and siding installation
300 Block South
- Continue wood-look siding installation on the courtyard side
300 Block North
- Continue trim and siding installation
400 Block
- Continue framing soffits for perimeter lighting
700 Block
- Tentative scaffold installation for upcoming skylight work
- Install red exterior panels
- Continue mechanical penthouse siding work
Main Courtyard
October 12–18
200 Block
- Continue trim and siding installation
300 Block North
- Continue trim and siding installation
700 Block
- Skylight demolition and installation
- Continue scaffold work for the skylight
- Continue red exterior panel installation
- Continue mechanical penthouse siding work
Main Courtyard
About the Project
The Building Envelope Project is designed to enhance the exterior of the Prince George Campus through energy-efficient upgrades, improved sustainability, and long-term infrastructure renewal. These improvements will help create a more comfortable and resilient campus for students, employees, and visitors.
This project is made possible with restricted capital funding by the Ministry of Infrastructure.
The Building Envelope Project supports CNC’s Strategic Plan (lhulh whuts’odutel’eh – Learning Together) under Priority 3.5: Rejuvenate College Infrastructure. Specifically, it supports objectives 3.5.1 through 3.5.4 by upgrading campus infrastructure, revitalizing learning spaces, improving sustainability, and helping reduce the college’s overall carbon footprint.
Key Highlights of the Project:
- Energy-efficient building upgrades
- Modernized campus exterior
- Improved long-term durability and sustainability
Project Timeline
- March 2025: Project mobilization and site preparation
- May 2025: Construction begins
- Summer–Fall 2025: Demolition and exterior renewal work
- Winter 2025–26: Interior and exterior finishing activities
- Spring 2026: Major exterior upgrades continue across campus
- Estimated Completion: May 2027
Impact on Campus
We are committed to minimizing disruptions during construction. Updates will be provided regarding:
- Campus accessibility
- Temporary disruptions and detours
- Changes to parking, entrances, and pedestrian routes
Our team is focused on ensuring that the impact on your daily experience is as minimal as possible.
Building Envelope Project FAQ
Why does some of the new siding look wavy?
Some members of the campus community may notice slight waviness or “ripples” in portions of the new metal siding. This effect, known as oil canning, is a common characteristic of flat metal siding and is widely recognized across the construction industry.
Oil canning is a visual effect only. It does not affect the strength, safety, durability, or weather protection of the building. The project team continues to monitor installation quality to ensure the work meets project requirements and industry standards.
The effect is often more noticeable in certain lighting and typically becomes less noticeable over time.
Read more about siding appearance