Stay informed with regular updates as construction progresses. We’ll keep you posted on project milestones, potential disruptions, and other important details.
Building envelope work continues across the Prince George Campus through early August. Current work includes landscaping, window installation, exterior wall upgrades, insulation, siding installation, painting, and exterior finishing.
Work is taking place in the 100, 200, 300, 400, 500, and 700 Blocks.
Accessible parking near the Main Entrance has been relocated until further notice to the crosswalk ramp, and a detour is in place for those walking from the east side.
Check the full map to see how campus blocks are connected and where work is taking place.
Expected Impacts:
🔊 Noise: Elevated noise is expected from canopy construction, window installation, insulation work, and exterior wall framing in the 300 and 400 Blocks.
🚧 Access: Temporary barriers, fencing changes, and localized detours may be in place near active work areas. Please follow posted signage and use alternate routes where required.
🪟 Window Installation: Window installation continues in the 300 Block North, including the connector between the 300 and 400/500 Blocks. Some work may occur during off-hours to reduce impacts on campus operations.
👷 Construction Activity: Landscaping, siding installation, insulation, painting, material deliveries, and exterior finishing continue across multiple campus buildings.
Please follow posted signage and allow extra time when travelling through construction areas.
Upcoming Activities
August 3–9
100 Block
- Prepare grades for new sod
200 Block
- Install insulation
- Install trim
300 Block South
- Continue concrete work at entrance canopies 🚧
- Install main tower panels
300 Block North
- Install crossover windows 🪟
- Continue window installation 🪟
- Install insulation
- Install air barrier
300 Block West
- Install insulation clips and girts
400 Block
- Install insulation clips and girts
- Install DensGlass wall panels
- Frame and insulate exterior wall above the windows
- Frame soffits for exterior strip lighting
700 Block
- Exterior cleanup
- Install finish panels
- Complete deficiency repairs
- Mechanical penthouse siding
Window Installation Schedule Day Shift (7:30 a.m. – 4:00 p.m.)
- August 6-7 : 300 Block West (1st and 2nd floors)
August 10–16
300 Block South
- Continue installation of main tower panels
400 Block
- Continue DensGlass installation
- Continue framing and exterior wall work
- Continue soffit framing for strip lighting
700 Block
- Continue strip lighting installation
- Continue finish panel installation
- Continue mechanical penthouse siding
- Continue deficiency repairs
Window Installation Schedule Night Shift (4:00 p.m. – 1:00 a.m.)
- August 10-11: Room 2-308 and 2-309A
- August 11-12: Room 2-390 (Sonography Computer Lab)
- August 13-14: Rooms 2-381, 2-382, 2-384 and 2-385 (Marketing & Events)
- August 14 & 17: Rooms 2-381, 2-383 and 2-387 (Marketing & Events)
August 17–23
300 Block South
- Continue installation of main tower panels
700 Block
- Continue strip lighting installation
- Continue finish panel installation
- Continue mechanical penthouse siding
- Continue deficiency repairs
Window Installation Schedule Night Shift (4:00 p.m. – 1:00 a.m.)
- August 19-20: Rooms 3-370, 3-371 and 3-337
- August 21 & 24: Rooms 3-336 and 3-337
About the Project
The Building Envelope Project is designed to enhance the exterior of the Prince George Campus through energy-efficient upgrades, improved sustainability, and long-term infrastructure renewal. These improvements will help create a more comfortable and resilient campus for students, employees, and visitors.
This project is made possible with restricted capital funding by the Ministry of Infrastructure.
The Building Envelope Project supports CNC’s Strategic Plan (lhulh whuts’odutel’eh – Learning Together) under Priority 3.5: Rejuvenate College Infrastructure. Specifically, it supports objectives 3.5.1 through 3.5.4 by upgrading campus infrastructure, revitalizing learning spaces, improving sustainability, and helping reduce the college’s overall carbon footprint.
Key Highlights of the Project:
- Energy-efficient building upgrades
- Modernized campus exterior
- Improved long-term durability and sustainability
Project Timeline
- March 2025: Project mobilization and site preparation
- May 2025: Construction begins
- Summer–Fall 2025: Demolition and exterior renewal work
- Winter 2025–26: Interior and exterior finishing activities
- Spring 2026: Major exterior upgrades continue across campus
- Estimated Completion: May 2027
Impact on Campus
We are committed to minimizing disruptions during construction. Updates will be provided regarding:
- Campus accessibility
- Temporary disruptions and detours
- Changes to parking, entrances, and pedestrian routes
Our team is focused on ensuring that the impact on your daily experience is as minimal as possible.
Building Envelope Project FAQ
Why does some of the new siding look wavy?
Some members of the campus community may notice slight waviness or “ripples” in portions of the new metal siding. This effect, known as oil canning, is a common characteristic of flat metal siding and is widely recognized across the construction industry.
Oil canning is a visual effect only. It does not affect the strength, safety, durability, or weather protection of the building. The project team continues to monitor installation quality to ensure the work meets project requirements and industry standards.
The effect is often more noticeable in certain lighting and typically becomes less noticeable over time.