Building Envelope Project Update
Current Updates
Building envelope work continues across the Prince George Campus, including skylight replacement, exterior siding and panels, stair and canopy work, soffit framing, and exterior lighting installation.
Work is taking place in the 200, 300, 400, 500 and 700 Blocks, the Main Entrance atrium, and surrounding exterior areas.
Skylight removal and replacement begins Friday, November 6, at the Main Entrance atrium and will continue over the coming weeks. Scaffolding installation takes place after 4:00pm.
Other upcoming activities include concrete sidewalk replacement near the 500 Block entrance, concrete work outside the 700 Block East Entrance, and exterior lighting installation in the 300 and 500 Blocks.
Check the full map to see how campus blocks are connected and where work is taking place.
Expected Impacts
🔊 Noise: Construction noise is expected from stair work, exterior finishing, scaffolding installation, and skylight replacement. Concrete grinding at the top of the new 300 Block stairs will be particularly noisy. Scaffolding installation takes place after 4:00pm.
đźš§ Access: The exits, bridge and loading dock on the north side of the 300 Block will be closed on Wednesday, November 4. The Main Entrance doors will be closed on Saturday, November 7 and Sunday, November 8. Sidewalk replacement near the 500 Block west entrance will not require the entrance to close.
đź‘· Construction Activity: Skylight replacement, exterior panels, black metal siding, stair finishing, canopy work, soffit framing and exterior lighting installation will continue through November. Concrete removal and replacement are also planned outside the 700 Block East Entrance.
Please allow extra time when travelling through campus and follow posted signage and detours.
Upcoming Activities
November 2–8
200 Block
- Continue installing black metal siding and soffits on the second and third floors.
300 Block
Continue concrete work on the new stairs, including stair treads and the middle landing.
Complete interior finishing around third-floor window frames.
Paint the shipping and receiving roll-up door and new masonry.
300 Block North
Grind concrete at the top of the new stairs and prepare the landing 🔊
Continue installing exterior trim and finished panels.
Install mechanical louvre bases from Wednesday, November 4 to Thursday, November 5.
Wednesday, November 4: Close the north-side exits, bridge and loading dock for mechanical louvre work.
300 Block South
- Continue canopy work near the courtyard entrance.
400 Block
- Continue framing exterior soffits for perimeter lighting.
500 Block
Continue installing exterior trim and finished panels.
Replace a section of concrete sidewalk near the west entrance between the gym and Dental Building. The entrance will remain open.
700 Block
Friday, November 6: Begin skylight removal and replacement.
Continue scaffolding installation after 4:00pm.
Begin limited removal of existing concrete and installation of new concrete outside the East Entrance.
Install the second-floor East Entrance door, which will remain available for emergency use.
Saturday, November 7 and Sunday, November 8: Main Entrance doors closed for maintenance.
November 9–15
- No construction work scheduled for Wednesday, November 11 (Remembrance Day).
300 Block North
- Continue installing exterior trim and finished panels.
300 Block South
- Continue canopy work near the courtyard entrance.
400 Block
- Continue framing exterior soffits for perimeter lighting.
700 Block
Continue skylight removal and replacement.
Continue exterior concrete work outside the East Entrance.
November 16–22
300 Block North
- Continue installing exterior trim and finished panels.
300 Block South
- Continue canopy work near the courtyard entrance.
400 Block
- Continue framing exterior soffits for perimeter lighting.
700 Block
- Continue skylight removal and replacement.
November 23 Onward
300 Block South
- Begin exterior lighting installation.
400 Block
- Begin electrical work for exterior perimeter lighting.
500 Block
- Begin exterior lighting installation.
700 Block
- Continue skylight removal and replacement, with the completion date to be confirmed.
About the Project
The Building Envelope Project is designed to enhance the exterior of the Prince George Campus through energy-efficient upgrades, improved sustainability, and long-term infrastructure renewal. These improvements will help create a more comfortable and resilient campus for students, employees, and visitors.
This project is made possible with restricted capital funding by the Ministry of Infrastructure.
The Building Envelope Project supports CNC’s Strategic Plan (lhulh whuts’odutel’eh – Learning Together) under Priority 3.5: Rejuvenate College Infrastructure. Specifically, it supports objectives 3.5.1 through 3.5.4 by upgrading campus infrastructure, revitalizing learning spaces, improving sustainability, and helping reduce the college’s overall carbon footprint.
Key Highlights of the Project:
- Energy-efficient building upgrades
- Modernized campus exterior
- Improved long-term durability and sustainability
Project Timeline
- March 2025: Project mobilization and site preparation
- May 2025: Construction begins
- Summer–Fall 2025: Demolition and exterior renewal work
- Winter 2025–26: Interior and exterior finishing activities
- Spring 2026: Major exterior upgrades continue across campus
- Estimated Completion: May 2027
Impact on Campus
- We are committed to minimizing disruptions during construction. Updates will be provided regarding:
- Campus accessibility
- Temporary disruptions and detours
- Changes to parking, entrances, and pedestrian routes
- Our team is focused on ensuring that the impact on your daily experience is as minimal as possible.
Building Envelope Project FAQ
Why does some of the new siding look wavy?
Some members of the campus community may notice slight waviness or “ripples” in portions of the new metal siding. This effect, known as oil canning, is a common characteristic of flat metal siding and is widely recognized across the construction industry.
Oil canning is a visual effect only. It does not affect the strength, safety, durability, or weather protection of the building. The project team continues to monitor installation quality to ensure the work meets project requirements and industry standards.
The effect is often more noticeable in certain lighting and typically becomes less noticeable over time.
Read more about siding appearance